Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Capital Improvements topic

No spam. Unsubscribe anytime.

Suffolk council reviews $533.8 million five‑year capital plan, addresses demolition and drainage concerns

2368947 · February 5, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Finance Director Charles Meeks presented the proposed fiscal‑year 2026–2035 Capital Improvements Program to the Suffolk City Council at a work session, saying the plan’s first five years total $533,800,000 and staff recommended sending the proposal to a public hearing in February.

Finance Director Charles Meeks presented the proposed fiscal‑year 2026–2035 Capital Improvements Program to the Suffolk City Council at a work session, saying the city’s recommended first five‑year program totals $533,800,000 and that the planning commission recommended forwarding the plan for council consideration.

The CIP document, Meeks said, is a 10‑year plan with emphasis on the first five years and is used as a financial planning tool to frame the operating and capital budgets. "The proposed 5 year CIP is $533,800,000," Finance Director Charles Meeks said, and he noted the document will be updated annually and the first year will be included in the city manager’s proposed operating budget.

The plan directs $402.4 million to general government projects, supported by $165.9 million in general obligation bonds, roughly $158.4 million in state and federal funds and $75.1 million in General Fund and capital reserve cash. Meeks said transportation projects account for about 47% of the general government portfolio; locally funded dollars are directed largely to public school projects (about $96.4 million, or roughly 40% of local funds). He described a mix of projects spanning parks, public safety, buildings, village and downtown initiatives and utilities.

Key projects and funding highlighted in the presentation include:

- Parks and recreation: $4.1 million for capital maintenance over five years; $3.2 million (second year) for roadway, parking and boat ramp construction at the former Brady’s Marina site; $1.4 million in FY26 for ball fields at the Driver complex; $600,000 in FY26 to establish a multipurpose field and walking trail at the East Suffolk Athletic Fields (separate demolition funding exists for the former school building).

- Transportation: local matches and awarded grants for Godwin Boulevard widening (local $1.25 million to match $8.6 million awarded), Route 17 widening (local $3 million to match $9.8 million awarded), Shoulders Hill phases 2–3 ($22.6 million FY26–28), a diverging diamond interchange at Godwin (local $1.75 million to match $12.9 million in state/federal funds), and Route 460 work (city awarded $30.1 million state funding and $2.1 million developer contribution for early phases; larger construction funding anticipated in later years).

- Public safety and fleet: $19.1 million for fire apparatus replacements and $6.8 million for ambulance replacements in the first five years; station replacements and upgrades were also programmed.

- Schools: a Northern Shores Elementary addition (about $11.1 million in FY26 plus $3.2 million in FY27) and a planned Elephant’s Fork Elementary replacement (approximately $61.1 million across FY27–29) were included.

- Utilities and stormwater: public utilities projects totaling roughly $101.8 million in the first five years, including $41.8 million for surface water treatment plant expansion and $28.7 million in water system upgrades; stormwater projects of $17.3 million including a Murphy’s Mill culvert replacement ($1.9 million) and Oakland drainage improvements (multi‑year work).

Council members asked for clarifications on specific items and the scheduling process. Vice Mayor Ward asked about the cemetery fund and how those fees are used; Meeks replied the city receives fees for burials into a perpetual‑care or cemetery fund and said, "the fund we're referring to is, specifically for the cemeteries that we own for ... perpetual care," noting the proposal would split the project funding about half from the cemetery fund and half from General Fund cash.

Several council members raised site‑specific and timing questions. Council Member Wright and others pressed to address safety concerns at the former Driver Elementary site (trailers and playground hazards) before the CIP’s formal adoption. The City Manager said staff could "get some rough estimates" and bring alternatives to council for consideration prior to the public hearing, and added that demolition and urgent safety fixes were being pursued outside the CIP where possible.

Council Member Williams asked whether the $600,000 budgeted for East Suffolk Athletic Fields included demolition; staff responded demolition funding and the demolition schedule are separate from the CIP line item for field work and that bids were scheduled, with demolition expected to be underway within roughly 60 days.

Transportation questions included whether a right‑turn lane to Burnham Manor would be included in the Route 17 plans. Staff advised that the turn lane had been added to 60% plans after earlier reviews and that staff could add a more specific description to the CIP narrative so constituents see the intended improvements.

Meeks closed by repeating that the CIP is a planning document, not the operating budget, and asked the council to adopt a motion to schedule a public hearing. Council members said they would schedule a public hearing for the council’s meeting in February to receive public comment and consider amendments before adopting the plan.

Votes at a glance

- Motion to go into closed session pursuant to Virginia Code §2.2‑3711(A)(1) to consider appointments and the performance of the city manager: approved 7–0 (Bennett: yes; Bartlett: yes; Johnson: yes; Williams: yes; Wright: yes; Vice Mayor Ward: yes; Mayor Duman: yes).