Board approves time extension and additional work as Zaragoza Street project moves toward closeout
Summary
The Laredo Investment Board accepted a no-cost time extension to finish final punch-list items for the Zaragoza Street improvements, approved a construction change order to upgrade utility enclosures, and authorized related landscaping and irrigation adjustments.
The Laredo Investment Board on Jan. 14 accepted a contractor time extension and approved change orders and coordination services needed to complete the Zaragoza Street public‑improvements project.
City and consultant staff told the board most construction is finished but one remaining supplier delay — custom stone caps and brick veneer for a small retaining/seating wall — prevents final closeout. Edward Ochoa, project manager with KCI, said the project team held a pre‑final inspection on Jan. 15 and issued a punch list to the contractor. “The contractor has done pretty much all of them already,” Ochoa said. “The only pending item is the stone cap and the brick veneer … we received the updated bid from the manufacturer yesterday … he’s gonna get that…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat