Council approves $2.26M construction-management contract for Lincoln Avenue widening

2361354 · February 19, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council unanimously approved awarding construction management, inspection and material testing services for the Lincoln Avenue and Jordan Road widening to Benesch for $2,261,888; the construction contract bids will be reviewed at the March meeting.

The Parker Town Council unanimously approved a $2,261,888 contract recommendation on Feb. 18 for construction management, inspection and material testing services tied to the Lincoln Avenue and Jordan Road widening project.

Why it matters: The contract funds consultant oversight needed during a major capital project that the town and Douglas County have planned for years; county funding of $9 million toward construction was cited and the project is designed to reduce congestion along a primary east-west corridor.

Public Works staff said the town publicly advertised a qualifications request in November 2024, received two responses, interviewed both firms and selected Benesch (presented in meeting as Benesch/Benesh/Benish in varied pronunciations) as the most qualified. Staff said Benesch will provide construction management and inspection and will use a subconsultant for material testing. The negotiated fee of $2,261,888 represents roughly 7.5% of the estimated $30 million construction cost, a percentage staff said is within industry norms.

Staff also updated council on procurement and schedule: the bid opening for the construction contract occurred earlier that day; staff will review bids and present a construction contract for council consideration at a March meeting. Staff estimated contractor mobilization in mid-to-late April and a contract completion date in or about October 2026. Standard daytime lane-impact hours are expected (staff cited a typical 9 a.m. to 3 p.m. window for on-road work), with limited night work to be coordinated as needed.

Councilmember Dyack moved to approve the staff recommendation and Councilmember Barrington seconded; the motion passed unanimously. Councilmembers praised the project as long-planned local infrastructure work; one councilmember noted the presentation contained a minor numeric discrepancy between the slide and the packet (staff confirmed a $700 difference between the reported trailing digits and asked staff to reconcile in the record).

Clarifying details: Douglas County is contributing $9,000,000 toward construction; Benesch was selected from two qualified firms; staff recommended the negotiated fee as appropriate; and construction management services will include inspection and material testing using a subconsultant. Staff said bids for construction came in under the engineer's estimate and that a construction contract will be brought to council in March.