Phase 3 bus-lot reallocation for District 3 moves forward after long planning period
Summary
The committee approved a Phase 3 sales-tax reallocation of $2,187,921 to construct a bus lot for District 3 (paving and a small driver facility); staff said work would start in March and finish in June of next year.
Get email alerts on the Phase3 Bus Lot topic
No spam. Unsubscribe anytime.
The Audit & Finance Committee approved forwarding to the regular board meeting a Phase 3 sales-tax reallocation that will fund construction of a bus lot for District 3.
Staff said the $2,187,921 project will provide pavement for bus parking and staff personal vehicles and a small facility for dispatch and driver restrooms/preparation. An RFQ has been advertised and proposals were due Feb. 13; staff plans to start construction in March and complete the project in June of the following year. Committee members noted the project’s long history in the district’s capital planning; staff said the bus lot had been under consideration for many years and is the final Phase 3 project to be executed.
A staff member clarified that some remaining Phase 3 funds were being swept from a small remaining project-management balance to final payment for the bus-lot construction; no additional ongoing Phase 3 funding to program management was proposed.
Ending: The committee unanimously approved moving the reallocation to the regular board meeting.