Councilors in the Village of East Canton addressed resident questions about recent water-system contracting and heard service-department updates after a large water main break that sharply increased daily usage.
A resident reading a message raised why the village had not sought additional bids for a water-tower job, noting that a DiPietro Construction bid was about $44,000 higher than the lowest bidder. Council members said Ohio procurement rules do not require competitive bids under certain dollar thresholds and that the village prefers local businesses when “apples to apples” comparisons can be made, but will review costs if an estimate appears “grossly out of line.” Council said no signed annual maintenance agreement with DiPietro was in place at the time and that one was under discussion.
Service department staff reported a major water break on a 6-inch line discovered after midnight when pump alarms did not reset; staff said the village used roughly 208,000 gallons by midday the day of the break compared with a typical daily usage near 115,000–117,000 gallons. The council heard the break was extensive and that crews repaired it overnight.
The council approved a motion to purchase a replacement electric heater for the pump house from Chroma Lock not to exceed $2,270.05. The motion was seconded and advanced with no recorded objections during the meeting.
Under other business, the council discussed grant-seeking for three priority areas: water infrastructure (lines, pump house), police staffing, and roads. Council members said they had contacted a consultant (Arbor Hill Consultant, Scott Savage) and discussed federal and state opportunities, including a Department of Justice police wage grant and the COPS program; staff said some grant cycles open in spring and require standard demographic and budget information.
Finance actions: the council approved invoices totaling roughly $82,006.69 and payroll totaling $17,025.91 by roll call.
The council scheduled an executive session to discuss wages and salary matters later in the meeting.
Votes at a glance: motion to purchase pump-house heater (approved); approval of invoices $82,006.69 (approved); approval of payroll $17,025.91 (approved).