County project manager reports final payments, approves change orders for local projects

2354469 · February 19, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County construction manager reported completion and closeout of the election storage building, sought and received commission approval for change orders on a search‑and‑rescue facility, and presented an additional proposal to add heat trace to gutters; commissioners approved electrical/doorknob and heat‑trace change orders.

JR, Fremont County project manager, updated commissioners on several facility projects and requested approval of change orders and equipment purchases related to those projects.

JR said the election storage building project is complete, all payments have been made and the project has been closed out and turned over to county staff. "That has been completed. All money has been paid, and that project has been closed out," he reported.

On the Vanderskircher search‑and‑rescue facility, JR said a small punch list remains and the 40‑day statutory wait for final payment runs in early March. He requested approval of change order invoice 2163 from Bonneville Builders for $8,539.74 to cover electronic door hardware and associated power work; commissioners moved, seconded and approved the change order.

JR also presented a proposal for heat‑trace cable to reduce ice buildup in north‑side gutters. The automatic option, which activates by temperature, carried an estimate of $4,615. Commissioners approved the heat‑trace installation as a change order; staff said the work would be recorded as an additional (third) change order and would affect contingency balances.

JR provided a preliminary accounting showing remaining contingency funds across several projects and said completed projects continue to leave the county with contingency balances available for retention release when punch list work is complete.

Ending: Commissioners approved the requested change orders; final retention and release amounts will be determined after the 40‑day wait period and completion of remaining punch list items.