Summary

County commissioners approved up to $78,000 from riparian-repair/protection funds (or fund balance if necessary) to cover a Clay County share of additional costs to finish judicial formation of the West Central Regional Water District, with staff noting the county may seek EPA reimbursement later.

County staff updated the Clay County Board of Commissioners on the judicial-formation process for the West Central Regional Water District and requested additional county funding to complete the work.

Staff said the initial estimate for formation work was about $300,000, but project costs rose and another roughly $500,000 is needed to complete the process. The board heard that the project team expects potential EPA funding by mid‑summer that could reimburse county contributions, but commissioners were asked to commit additional county funds now so work can continue without delay.

Under the proposed cost‑share approach — the same percentage split used for the initial ask — Clay County's requested additional contribution ranged from $58,500 (for a smaller extra request) up to $78,000 if the larger supplemental need materializes. County staff and commissioners discussed potential use of riparian-repair/protection aid under Minnesota law as a funding source; County Attorney/administration staff provided a preliminary, cursory review of Minnesota Statute 103F.048 and said it did not obviously prohibit the use, though staff did not offer a definitive legal opinion at the meeting.

Commissioner Kavanagh moved to approve additional funding up to $78,000 from riparian aid to complete the judicial formation; Commissioner Bair seconded. The motion passed by voice vote and the board instructed staff to return with any necessary follow-up if the funding source needs to change to general fund balance.

Staff said the expectation is that EPA grant funds, if awarded this summer, can reimburse the county once received; until then the requested additional appropriation would allow the project to continue on schedule.