Commission establishes $69 million SR‑99 bond reserve; San Joaquin Valley leaders urge faster use for shovel‑ready projects
Summary
The commission approved a $69 million prudent reserve for the State Route 99 Proposition 1B corridor program and agreed to review the amount every three months. Regional officials urged a smaller reserve or a delay to allow immediate programming of shovel‑ready projects such as the Pellandale interchange in Modesto.
Get email alerts on the Sr99 Reserve topic
No spam. Unsubscribe anytime.
The California Transportation Commission approved a $69,000,000 reserve for the State Route 99 corridor bond program and agreed to re-evaluate the reserve on a three-month cycle, commissioners said.
Caltrans proposed the reserve to safeguard funds for projects in construction funded by the SR‑99 Proposition 1B program. Caltrans staff told the commission that roughly $699,000,000 in SR‑99 construction capital is currently under contract or will be under construction and that a prudent reserve would help address unforeseen construction cost increases on projects in the corridor.
"The State Route 99 bond funds have provided for 17 projects to be funded through construction," a Caltrans presenter said, noting that most counties along the corridor lack local sales-tax measures that could be tapped to cover supplemental costs. The department recommended setting aside $69,000,000 from accrued program savings and reexamining the reserve at least every three months to allow additional projects to be moved forward as risk declines.
Regional officials pressed for a smaller holdback or a delay in action so that shovel-ready projects can proceed. "We ask that you lower the $69,000,000 reserve to $18,000,000 or postpone your action on this item until December," said Aaron Hakimi, executive director of the Kern Council of Governments, citing concern that a large reserve will prevent programming of additional projects despite accrued savings. Hakimi said local agencies, including the city of Bakersfield, had committed to cover any overruns on projects they would receive.
Carlos Shamson, interim executive director of the Stanislaus Council of Governments, urged flexibility and local commitment, noting the Pelandale interchange in Modesto has been ready for programming for months. "It is really our collective hope that the department and the commission maintain the maximum flexibility with regards to any project cost savings to allow the San Joaquin Valley to continue to deliver projects," Shamson said.
Commission staff and the deputy executive director replied that the reserve is meant as a short-term risk-management tool to ensure contracts already awarded are fully funded, and that as projects are contracted or move into construction the commission will have more precise data and be able to release additional savings. The commission approved the staff recommendation with the commitment to return in three months for re-evaluation.
As part of the same sequence of actions, commissioners added the Route 204/Beardsley Canal (Route 99 Winding) project to the SR‑99 program and approved its project baseline agreement, using available SR‑99 savings to fund the addition.
Key quantitative details cited in the discussion: Caltrans reported about $699,000,000 in SR‑99 construction capital currently in or near construction; staff estimated approximately $115,000,000 in savings available by December; the proposed reserve was $69,000,000 and staff said it represents roughly a program-level prudence amount tied to outstanding construction allocations. Commissioners agreed to the three-month review to determine whether the reserve can be reduced and additional projects programmed.
The commission's action was taken by voice vote; the transcript records the motion as having passed. Staff said it will return with updated risk evaluations and recommendations for any changes to the reserve in future meetings.