Magnolia ISD reports construction progress on 22-bond projects; JROTC and event building cleared by fire marshal
Summary
District staff told the board the JROTC and event buildings passed fire marshal inspection, artificial turf has been installed at the football stadium and Parkway Junior High is on schedule for May delivery.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Magnolia Independent School District staff updated the board on progress for several projects funded by the district’s 2022 bond program, reporting completed fire marshal inspections for two ground-up projects, the installation of artificial turf at the football stadium and continued finishes and life-safety testing at Parkway Junior High.
Why it matters: The bond-funded construction affects campus capacity and facilities used by students and the community. Progress updates provide a timetable for school openings and help the board and public track final work and closeout activities.
What staff reported
Mr. Bruner presented the update, saying the district completed fire marshal inspections on the JROTC building and the new event building the previous week. He said Parkway Junior High remains on schedule for a May delivery, and staff has begun landscaping to ensure establishment before August.
"We got the fire marshal inspection completed last week. We also got the fire marshal inspection completed on the new event building," Mr. Bruner said while reviewing project photos. He added that finishes — walls, ceilings, and flooring — are moving quickly and that life-safety systems are being tested.
The presentation included photographs and progress notes for interior spaces: main canopy and entry, corridors, library areas with upcoming carpet installation, cafeteria and gym flooring, band hall storage and classroom wings where flooring and marker/tack-board installs are finishing. Mr. Bruner also showed the event building interior and said the floor had been ground and was scheduled to be polished.
District next steps
Staff said they will continue finish work and life-safety testing and move toward final inspections and occupancy for the completed buildings. Parkway Junior High’s scheduled May delivery remains on the timeline shared to the board; district staff will return with additional closeout figures and possible additional deductive change orders as allowances are reconciled.
Ending
Board members thanked contractors and district staff for the work; no board action was required on this update beyond receiving the report.