Stormont Vail renovation: county project team reports progress, $20 million cap and 2028 deadline cited
Summary
Project representatives told the commission that substantial mechanical upgrades are complete, other major projects are underway, and the county’s agreement limits public funds to $20 million with a January 2028 deadline for completion.
Get email alerts on the Healthcare Facility Capital Projects topic
No spam. Unsubscribe anytime.
Commissioners received a multi-topic update on ongoing renovation work at the county‑affiliated hospital campus and the use of the county’s $20 million allocation for capital improvements.
The project representative reported completion of several major mechanical projects: air‑handler replacements on a main floor radiology suite and SPD kitchen, two new boilers that performed during the cold snap, and work underway to modernize heating, cooling and electrical systems in the MAB 1 building. A major electrical modernization of legacy switchgear and panels was estimated at about $2.8 million; replacing or repairing cooling‑tower components and wastewater piping were described as forthcoming priorities.
Project staff and county members said the county’s funding agreement provides a $20 million allotment for renovations and that the parties expect the work to be completed under that cap. Participants said the agreement gives Stormont Vail discretion to decide whether to proceed with additional work if the $20 million is exhausted; commissioners were told that the county and hospital agreed timeline extends to January 2028.
Commissioners pressed for an itemized, up‑to‑date expected‑final‑cost (EFC) estimate and for a list of projects that will be left undone if the $20 million is insufficient. Project staff said the original assessment dated to 2019 and acknowledged that inflation increases and updated scope will likely leave some items—such as parking-lot repairs—unfunded under the $20 million cap. County members said they will ask Stormont Vail for a prioritized list showing which items will be completed and which likely will not.
County and hospital representatives said much of the work already completed improved building performance and resiliency: upgraded boilers and air handlers increased capacity and control, reducing long‑standing temperature and comfort problems, staff said.
County commissioners asked the Public Building Commission (PBC) to draft a specific letter to Stormont Vail identifying which items the county wants clarity on and requested a future briefing with a cost‑to‑complete list and recommended priorities.