Portsmouth completes 2024 bond projects; PHS roof identified as immediate priority
Summary
District staff reported certificates of substantial completion for summer 2024 bond projects at elementary schools and said the Portsmouth High School roof is a current priority; Marin Construction was named as contractor for upcoming PMS bathroom work.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
District officials reported that the Portsmouth School Department has obtained fully executed certificates of substantial completion for its summer 2024 bond projects, work that included classroom HVAC replacements at Hathaway and Melville, two new sets of student bathrooms and a new elevator at Hathaway, and additional bathrooms and HVAC work at Melville.
Facilities Director George Simmons told the committee his team assembled a comprehensive list of facility needs after walkthroughs with building administrators. "There's lots of these things are more of a continued process," Simmons said, noting that many items are carryovers that require continued attention during vacation periods and summers.
The committee also confirmed that Marin Construction was selected and approved previously by the full committee to complete the PMS bathroom project scheduled for summer 2025. District staff said Marin Construction has begun coordinating with school leadership and town officials to prepare for that work.
Why it matters: The district said full occupancy has been achieved at completed sites, with only minor items outstanding with contractors, but the high school roof was called out as the district's main facilities priority and will receive focused attention and coordination with town officials. District staff said they are working on repairs as quickly as possible and will provide updates during subsequent meetings.
Discussion and context: The facilities review formed part of the district’s goal number 3 (ensuring safe, healthy learning environments). Simmons said his inventory draws on conversations with building administrators and facilities staff and includes both low‑level and higher‑level projects. The district noted that the PMS bathroom project was bid and that the full committee previously approved the contractor; work is planned for the summer of 2025.
Ending: District staff said they will continue to monitor contractor punchlist items on completed projects and intend to bring periodic updates to the committee; the PHS roof will be on the agenda for future meetings and staff will coordinate town/district actions as they proceed.