Commission approves $30 million allocation for Gerald Desmond Bridge oversight
Summary
The commission approved a $30 million allocation to support project oversight of the Gerald Desmond Bridge replacement in the Port of Long Beach. Port and agency representatives briefed commissioners on procurement, budget categories and oversight arrangements for the design'build project.
Get email alerts on the Gerald Desmond Bridge topic
No spam. Unsubscribe anytime.
The California Transportation Commission approved a $30 million allocation to cover oversight costs for the Gerald Desmond Bridge replacement project at the Port of Long Beach.
Port of Long Beach representatives outlined procurement and budget status. The design'build procurement produced multiple qualified teams; the successful proposal was selected following a best'value evaluation. Project features include a twin single'tower cable'stay bridge with three travel lanes in each direction and a dedicated bike/pedestrian path. The Port and project team said utility relocation remains a primary potential cost risk as detailed design advances.
Why it matters: The Gerald Desmond Bridge is a major freight corridor project for Southern California; the new bridge will be transferred to the state on completion. The allocation covers oversight functions tied to the complex design'build procurement and early contract work.
Vote and next steps
The allocation request was moved, seconded and approved by voice vote. Port staff said remaining approvals and contract documents were scheduled for the Port of Long Beach board in mid'July and that notice to proceed and construction activities are planned to follow later in 2012 and 2013. The commission will continue to receive budget and procurement updates as the project advances.