Gates Chili board hears progress report on 'Building Brighter Futures' capital project
Summary
District staff reported construction progress on middle school music space, athletic fields and office renovations and reviewed budgets for phases 1–3 of the 2022 capital improvement program.
The Gates Chili Central School District Board of Education received a progress update on the district's 2022 capital improvement program, known as the Building Brighter Futures project, focusing this month on the final middle school music space and Phase 2 site and building work.
District project staff reported that Phase 1 work — which included the district office, high school and technology spaces — is substantially complete and that work in the middle school music area is ongoing. Contractors from DCI, the district's general contractor, have installed roof metal decking and begun foam insulation. Interior masonry and metal stud walls are in place, and…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat