Waterbury Phase 2 reaches 90% design; right-of-way and federal changes create next steps
Summary
City of Waterbury reported that Phase 2 of the Naugatuck River Greenway is at 90% design with constructability reviews starting; the team will issue an RFP for right-of-way appraisal work after recent changes to DOT support for ROW on greenway projects.
Get email alerts on the Waterbury Phase2 topic
No spam. Unsubscribe anytime.
Judy Mancini, City of Waterbury adviser, said the Waterbury Phase 2 design is nearly complete and that the project team is preparing right‑of‑way procurement steps.
"90% design has been submitted. Constructability reviews will be starting," Mancini said during the steering committee meeting. She added: "We'll be issuing an RFP for right of way appraisers."
Mancini told committee members the city and consultants have reviewed a right‑of‑way ramp submittal and that, as a procedural change, the Connecticut Department of Transportation has stopped assisting with right‑of‑way work on greenway projects; project teams must now directly manage appraisal and acquisition work. Mancini said the team is navigating federal and state contract changes while advancing project design.
During committee Q&A, Mancini put the Waterbury greenway total at roughly seven miles when complete.
Ending: No formal vote was taken. Staff said they will proceed with constructability reviews and next procurement steps while monitoring federal program changes.