Avon council approves $491,000 in design changes for Burnett Park and pickleball site
Summary
The Avon Town Council approved two contract amendments to finish design for Burnett Park (including restroom utility work) and to complete engineering for new pickleball courts near Avon Avenue, totaling roughly $491,000.
Get email alerts on the Parks And Recreation topic
No spam. Unsubscribe anytime.
The Avon Town Council on an 5-0 roll call approved two contract amendments to finish design and utility work for Burnett Park and to complete engineering for a new pickleball court site near Avon Avenue.
Council members voted to approve change order 3 for the Burnett Park project, adding additional survey work, architectural design and sanitary/water engineering, and a second contract for design work for pickleball courts. Town staff said adding water and sewer now would allow restrooms and a small maintenance area to be built with initial construction, rather than retrofitting later.
Planning Director Linda Albran and Parks and Recreation Director Shelby Bridal presented the changes to the council, saying donated fill on the Burnett Park site required a resurvey and that restroom utilities would better support staffing and long-term use. Albran said the change order increased the park contract by roughly $47,000 and revised the contract total to approximately $357,982 (discussion in the meeting corrected the precise change order amount to $355,009.82). The pickleball design contract was presented as roughly $135,925 in design fees; council packet materials showed a larger construction budget for the courts (about $800,000) coming from the parks bond.
Council members discussed timing and the priority of including restrooms for accessibility and for older players who use pickleball facilities. Parks staff said they have coordinated with the school corporation to repurpose old school tennis courts on Avon Avenue as the site for the new courts; the school has agreed to donate the land and the town will design and build the improvements.
Motion language recorded at the meeting asked the council to approve the two change orders “as presented.” The clerk conducted a roll call with unanimous approval recorded.
The approved actions move both projects to final design and bidding, with pickleball construction expected to occur in a later year because of high contractor demand.
Supporting details from staff included the $355,009.82 change order figure for Burnett Park and $135,925 for pickleball design; the projects are funded through the parks bond and related sources noted in the project cost breakdown provided to council.