City hall construction: staff outlines CMAR approach, early release packages and summer 2027 target
Summary
Owners’ representative and staff explained the construction manager at‑risk (CMAR) approach for the new city hall, early release packages to reduce inflation risk, monthly reporting, and a target completion in summer 2027.
City of Franklin staff and the owner’s representative updated the Board of Mayor and Aldermen on the schedule, procurement approach and near‑term decisions for the new city hall during the Feb. 25 work session.
Owners’ rep Chris Kepper and staff described a three‑package CMAR (construction manager at‑risk) strategy with early release packages (ERPs) so work can begin earlier on abatement, demolition,…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat