Keller Sports Park at 53%: board asked to propose names for two multipurpose fields

2310276 · February 14, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff reported Keller Sports Park construction at roughly 53% complete and set a roughly 14-month schedule to finish major elements. The board was asked to propose names for two new multipurpose fields and to align suggestions with the park's retro/historical design and upcoming public art program.

City staff told the Keller Park and Recreation Board that Keller Sports Park construction is about 53% complete and that major elements remain on a roughly 14-month schedule.

Construction update and timeline

At the meeting staff said fencing and nets are up on several pads; brick and shade structures are under construction; synthetic turf is down on one soccer pad; utility work (water, sewer and electrical) is ongoing; the north multipurpose parking lot is complete and the north multipurpose field was…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans