Council rejects Gay Street closure bids; staff to rebid project
Summary
Engineers recommended rejecting two bids for the Gay Street closure project after the low bidder’s submission lacked required items; council recorded a motion to reject all bids and directed staff to rebid.
Get email alerts on the Local Infrastructure topic
No spam. Unsubscribe anytime.
West Chester borough staff recommended rejecting both bids received for the Gay Street closure project and rebidding the work to obtain more competitive pricing.
Kelly Groff, the presenting engineer, told council that two bids were received on Jan. 9 and that “the apparent low bidder had various items missing from their bid package,” and that staff believes rebidding could attract more competitive pricing. Council moved to reject all bids; the motion was recorded in the meeting as approved without opposition.
Staff clarified that part of the project is funded through American Rescue Plan Act dollars and that the borough must spend those dollars before the end of 2026. Staff and council discussed scheduling and the need to rebid promptly so work can proceed within the grant timeline.
Next steps: Public Works will prepare a rebid and return with a proposed procurement schedule and updated timeline. The rebid will include the business district feedback on preferred construction timing (businesses requested work take place in summer rather than October or November).