C TRAN briefing: light-rail O&M could require local funding; board to revisit decision in March

2304425 · February 13, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

C TRAN staff updated La Center council on the Interstate Bridge Replacement program’s transit assumptions, saying annual operations-and-maintenance (O&M) for light rail could be about $21.8 million (2033 opening-year estimate) and that the C TRAN board will reconsider its level of financial participation at its March meeting.

C TRAN representatives briefed the La Center City Council on the Interstate Bridge Replacement (IBR) program’s transit assumptions and the agency’s internal debate over whether C TRAN should contribute to light-rail operations and maintenance.

Scott Patterson, representing C TRAN, told the council the most recent IBR planning materials assume a 2033 opening year and estimate combined light-rail and incremental express-bus O&M at roughly $21.8 million in the first year of operation. Patterson said TriMet’s modeling assumes about 25% farebox recovery and that TriMet’s Oregon-side share would be about $8.3 million in the opening year while the Washington-side light-rail share would be about $6.8 million (express-bus additions on Washington’s side were estimated separately at roughly $443,000). Patterson said C TRAN earlier adopted restrictive language that would not obligate it to pay O&M but that, in November, the board directed staff to study more-flexible language allowing C TRAN to “may participate” in O&M funding. That change has prompted renewed debate; the board will take up a motion to return to the original, more-restrictive language at its March meeting so member jurisdictions can provide input.

Why it matters: Patterson said the Federal Transit Administration’s Capital Investment Grants (CIG) program is expected to be the largest single federal capital source for the project but pays capital only (not local O&M). The FTA evaluation requires updated capital-cost and ridership forecasts before a project rating can be assigned; those updates — and a planned capital-cost update — are expected this year. Patterson said decisions about committing to long-term O&M share typically must be resolved within roughly three years to meet FTA process timelines if the project proceeds to a federal capital grant.

Key figures presented by C TRAN staff (taken from the presentation): an opening-year O&M estimate of about $21.8 million (2033); expressed split roughly 55% of new light-rail track in Oregon and 45% in Washington; TriMet farebox recovery assumption ~25% (reducing local net O&M needs); estimated annual express-bus O&M in the presentation about $1.5 million. Patterson stressed these are planning-year projections subject to update pending the capital-cost and ridership analyses.

Council reaction and next steps: Council members asked for up-to-date ridership and systemwide numbers that reflect post-pandemic patterns; Patterson agreed to provide systemwide and historical (2019 and current) ridership data to the council. Council members also discussed tolls and other revenue sources; Patterson said toll revenue assumptions in the IBR program are not intended to cover transit O&M. He said, absent new state or federal commitments, local sales-tax measures would be among the options for funding local O&M shares if C TRAN or its partners decide to proceed.

Public comment: Two callers raised concerns. Margaret Tweed (Camas) told the council Camas City Council had adopted a resolution opposing light rail across the I-5 Columbia River Bridge and noted differences in capital and operating cost estimates between light rail and express bus. Melissa Platt (La Center United) gave an unrelated community-center events update earlier in public comment.

What’s next: Patterson said the C TRAN board will revisit language and possible commitments at its March meeting. Council members asked staff to prepare materials and public outreach options to assess local sentiment before C TRAN’s board decision. No formal action was taken by the La Center City Council at this meeting on funding for the IBR transit component.