Board awards $3.53 million package for summer 2025 school renovations

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved a recommendation package for summer 2025 renovations across multiple Southgate schools, with presenters saying the bids came in under a $4.16 million budget and recommending contracts totaling $3,534,767.

The Southgate Community School District Board of Education voted to approve a renovation award recommendation package for multiple district sites totaling $3,534,767, presented as the recommended total project award for summer 2025 work.

Gary Campbell, Planner and RealPoint (spokesperson for the project team), and Jason Hardy of Southgate Community Schools presented the recommendation covering work at Anderson High School, the Anderson Field House, Davidson Middle School, the Garris Robotics lab, and Northpointe Elementary. Campbell described scope items including lockers and flooring at Anderson High, locker-room renovations, fieldhouse work, a Davidson gym lobby entrance and exterior media-center lighting, the Garris Robotics lab layout, and a new air handler unit for Northpointe's media center.

Campbell said construction documents were issued on Jan. 3, 2025, sealed bids opened Jan. 23 and post-bid interviews occurred Jan. 27–30. He said the project team recommended the firms in Granger Construction's Guaranteed Maximum Price (GMP) proposal (attachment 3). Campbell stated a total project budget of $4,158,115 and reported the recommended award amount of $3,534,767; he characterized that outcome as coming in under budget and enabling the district to pursue additional projects. He also identified components included in the award figure: Granger Construction's GMP staffing/bond/insurance amount of $622,491 and hard contractor costs of $2,647,524.

Board members asked about the Garris Robotics layout; presenters said they would share the blueprint in the board packet for privacy. A question about the district's overall referendum or bond totals produced a clarification that the renovation package referenced the $3.53 million number (not the larger bond totals discussed elsewhere). Campbell attributed the favorable bids to strong bidder coverage and coordination between superintendent Irvine, Jason Hardy, TMP Architecture and Granger Construction.

A motion to approve the Southgate 2025 renovations award recommendation package not to exceed $3,534,767 was made (mover recorded on the transcript) and supported by Mr. Green; the board approved the motion by voice vote. The transcript contains multiple budget figures in the presentation, including the $4,158,115 budget figure and contractor line items; a presenter also referred to a "total project actual cost" number that is inconsistent in the transcript and requires confirmation from the district's final contract documents.

The approved package includes allocation for construction manager/general contractor staffing, insurance and bonds, construction-manager contingency and owner contingency. The board did not specify additional reporting or assigned follow-up tasks during the meeting.