The Permanent Public Building Committee voted unanimously to release approximately $1,324,000 in unborrowed funds from the Public Safety Complex and Fire Station No. 2 project so the town manager can place the amount on the upcoming annual town meeting warrant.
Get email alerts on the Public Safety Complex Closeout topic
No spam. Unsubscribe anytime.
The Permanent Public Building Committee voted unanimously Monday to release approximately $1,324,000 in unspent, unborrowed funds from the Public Safety Complex and Fire Station No. 2 project so the town manager can place the amount on the town meeting warrant.
The committee chair, Richard Cream, moved the release at the committee’s Feb. 10 meeting. Hank (town staff) said the amount represents money that had been authorized but not borrowed for the project, and that most of it stemmed from COVID-related allowances that were not ultimately spent after requirements eased. "The remaining funds are approximately $1,324,000," Hank said.
The motion instructed the committee staff to document the total project budget, how much is being released and the fact that the project closed under the approved appropriation so that town meeting members unfamiliar with the project could understand the context. George Kent seconded the motion; a roll-call vote recorded ayes from Stuart Chandler, Lynn Denninger, Bob Germany, George Kent, Erwin Silverstein, Tom (town official), and Chair Richard Cream.
The committee and staff said final closeout adjustments — for example, small outstanding charges or borrowing costs — could change the figure slightly. Hank recommended the committee describe the amount as "approximately" $1,324,000 for that reason.
Why it matters: the release returns authorized but unborrowed funds to the town for reallocation at town meeting. Committee members framed the vote as a transparency measure to show the project finished at or under its approved budget.
The committee closed the item after thanking Town staff for finalizing the account and confirming the paperwork route: a memo from committee staff to the town manager with copies to finance and the committee.