Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Fluor says LEAP construction is under way in Lebanon; cites cold-weather delays, new safety and community efforts

2281852 · February 11, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Fluor Corporation representatives told listeners on a Feb. 2025 Lebanon City podcast that construction at the Eli Lilly LEAP campus on the city’s north side is making steady progress but remains behind the original schedule because of extreme winter weather.

Fluor Corporation representatives told listeners on a Feb. 2025 Lebanon City podcast that construction at the Eli Lilly LEAP campus on the city’s north side is making steady progress but remains behind the original schedule because of extreme winter weather.

Todd Dando, a Fluor Corporation representative, said “we're currently just under 10%… we're probably somewhere around the 8% complete, on construction,” and that “the design for the project is over 50% now, nearing 60%.” He told host Joe LePage the project is about a month to two months behind schedule because of cold weather and that 2025 will be the year the team attempts to make up that time.

The update matters to Lebanon because the LEAP campus is a large biotech investment in the region that will affect local traffic, employment and nearby residents. Fluor, which is serving as a construction contractor on the project, described steps to…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans