Board approves personnel, construction and playground contracts; MASB vote selected

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Trustees approved the consent agenda and several contracts tied to the new junior high, electrical and foundation change orders, playground upgrades funded with grant money, and cast the district's vote for a MASB director candidate.

At its meeting, the Clarkston Community Schools Board of Education approved routine and contract items including personnel changes, a technology contract for the new junior high, construction change orders, playground upgrades and the district’s vote for a Michigan Association of School Boards (MASB) Region 8 director.

The board approved the consent agenda and personnel changes by voice vote. Trustees also voted to cast the district’s MASB Region 8 ballot for Roderick Means of Westwood Community School District for a three-year term.

Construction and contracts

- The board approved a contract with Complete Interactive Technologies Incorporated for $292,916.42 with an additional 10% construction contingency of $29,292 for work tied to the district’s new junior high building.

- Trustees approved change orders for Metro Electric (bulletin no. 4) in the amount of $71,728 and additional helical pier foundation work for JJ Barney in the amount of $50,372; both amendments were described as related to new junior high construction.

Playground upgrades

The board approved a recommendation to purchase playground equipment from Fun Incorporated for $103,000 and concrete sidewalks from Alvinelli for $39,800, and to carry a contingency/allowance of $96,780, for a total recommendation of $239,580. District staff said the playground work is largely funded by GSRP startup grants that must be spent by June 30; the contingency covers removal, disposal, mulch and fence work yet to be contracted.

Votes and procedures

Motion movers and seconders were recorded as “made and supported” in the meeting; votes were taken by voice and each motion was declared carried. No roll-call tallies were read into the record for these items.

What’s next

Staff will proceed with contract administration and procurement consistent with the approved contingencies and will return to the board if additional authorization is required.