District shows progress on Johnson Field athletic complex and next-phase facility renovations
Summary
Board presenters described ongoing work at Johnson Field — including 16 inches of gravel fill, precast end-zone buildings, turf field plans and an estimated first-week-of-August completion — and previewed Project C gym/weight-room renovations with bids due Feb. 20 and construction expected to run into mid-2026.
Get email alerts on the Facilities And Construction topic
No spam. Unsubscribe anytime.
District staff and project designers updated the School Town Speedway board on athletic and facility construction projects at the Feb. 11 meeting, showing renderings and recent site photos and describing timelines, scope and budget status.
The Johnson Field athletic complex (referred to in the presentation as Project A) includes a turf football field with a center graphic, new locker rooms, two concession stands, public restrooms, visiting locker rooms, an athletic training room and meeting space. Staff said 16 inches of gravel have been placed as base fill, precast components for the end-zone buildings are installed, and utility work and drainage are in place. Target completion for the first phase remained the first week of August; presenters said permits have gone through and work will continue as weather allows. The project presentation noted the first bid for this phase came in $300,000 under budget.
Project C — the former Ox Gym renovation and new weight room — is out for bid with a Feb. 20 bid date and a planned construction start in late February; staff said the projected duration would run through June 2026, and the renovation will include multiple indoor courts (two wooden courts and one rubber court), batting cages, a walking track, a 4,000-plus-square-foot weight room, renovated locker rooms, band practice space and support/storage areas. The renovation will affect parking and require temporary reallocation of practice space for teams during construction.
Designers and staff discussed security and daily/venue use: an “airlock” vestibule at Door 13 was shown to allow separation of school operations from public event access, and concessions and weight-room access were designed with windows and circulation to support weekend tournaments while keeping other school areas secured. Staff said some activity scheduling and temporary accommodations for teams will be necessary while construction is under way.
Provenance: information and photos were presented in the meeting by staff and named contractors/design firms (Schmidt, Myronasia, Verdes) and by on-site contacts (Eric Roseborough and Dan Mapple/Maple), as recorded in the transcript.