Planning director corrects record on Safe Streets for All grant; NEPA review delayed consultant procurement timetable
Summary
Planning Director Lee Poulliot read a communication clarifying the Safe Streets for All grant budget and timeline, saying the $400,000 project budget includes $320,000 FHWA award and $80,000 local match, and that National Environmental Policy Act (NEPA) review delayed consultant contracting but the city remains on track for a Feb. 2026 finish.
Get email alerts on the Transportation Grant topic
No spam. Unsubscribe anytime.
Planning Director Lee Poulliot read a written communication into the Feb. 3 City Council record to correct public comments about the cityโs Safe Streets for All (SS4A) planning grant and to outline a project timeline that was delayed while federal NEPA questions were resolved.
Poulliot said the project budget totals $400,000: $320,000 in federal grant funds from the Federal Highway Administrationโs SS4A program and an $80,000 local match. He said earlier public comments had misstated that the council appropriated $720,000; the correct appropriation actions were acceptance of the $320,000 grant and appropriation of $400,000 to the grant account to pre-fund expenditures that will be reimbursed by FHWA as costs are incurred.
The director provided a timeline of the grant process: initial application in August 2023, award announcement in December 2023, grant acceptance and revisions through early 2024, NEPA-related pause and contract revision in midโ2024, final grant agreement executed August 2024, and RFQ release for consultants on Jan. 2025 with responses due Feb. 6, 2025.
Poulliot acknowledged the NEPA process created a scheduling delay because SS4A planning-only grants required additional federal review before contract execution. He said the Planning Department released a request for qualifications on Jan. 2025 and expects to select a consultant following responses due Feb. 6, 2025. "While addressing the NEPA process did take some time, the city remains well positioned to complete its project by the contractually agreed-upon February 2026 deadline," Poulliot wrote in the communication.
The council voted to place the communication on file. Poulliotโs letter reiterated that the city will be reimbursed $320,000 by FHWA upon completion of grant-funded expenditures and that the cityโs net local investment will be $80,000.