County utilities reported a supplier-related delay on the Rolling A wastewater treatment-plant expansion, extending the contractor’s schedule by approximately seven months from Sept. 2025 to April 2026; project contingency and change orders were discussed.
Lyon County utilities staff told commissioners on Feb. 6, 2025, that the county’s Rolling A wastewater-treatment-plant expansion — a $24 million project to increase capacity from 1.0 million gallons per day (MGD) to 1.4 MGD — is under construction but experiencing schedule delay tied to a key supplier.
Kishore Panga, utilities engineer, summarized multiple utility projects and reported the Rolling A expansion had been under construction since October 2023 and had progressed satisfactorily until a major supplier missed contractual deliveries. The general contractor…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat