West Des Moines lays tentative timeline for E. P. True/Bridgewood extension; construction planned to start in 2025

2236222 · January 21, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

At a Jan. 21 public hearing the city outlined an alignment and a near-term plan for completing the E. P. True extension to Grand Prairie Parkway, but engineering and funding steps remain before work begins.

The West Des Moines City Council held a public hearing on Jan. 21 on the proposed extension of E. P. True and Bridgewood Boulevard and received a tentative engineering timeline showing construction could start in 2025 and finish in 2026.

The city engineer, Brian Hemestad, told the council the city has a tentative alignment for extending E. P. True into the area near Grand Prairie Parkway and is "working on right of way acquisition for EP True" and plans to start construction in 2025. Hemestad added the city has no funding committed yet to extend the roadway further west beyond the alignment and will move to construction "until some development occurs." "We plan to start construction next... 2025," Hemestad said when describing the schedule.

Why this matters: The alignment will serve planned growth in southwest West Des Moines and provide access needed for future school and residential projects; Hemestad noted the planned road will connect through property recently purchased for Waukee Community Schools' third public high school.

Public questions and city response

Jill Griffith, a resident representing Davis Estates Limited, asked whether the EP True extension would require additional property acquisition and when the extension would connect fully to Grand Prairie Parkway. Hemestad said the design work is advanced enough to show an alignment, that right-of-way acquisition is underway and that the city expects to start construction in 2025 and complete the connection in 2026. Hemestad also said the city will not move forward on construction before development activity or funding justify the next steps.

Council action

The council voted to approve a resolution authorizing acquisition of agricultural property needed for the extension (Item 6C). The vote was recorded as 4-0 in favor.

What to watch next

Staff said they will continue right-of-way negotiations and complete design before any construction contracts are advertised. Residents and property owners seeking the tentative alignment or right-of-way details were told to contact the city for the design maps and schedule; a councilor asked staff to share the tentative alignment with property owners who raised questions during the hearing.

Formal action

- Item: E. P. True and Bridgewood Boulevard extensions (acquisition of agricultural property). Outcome: Approved. Vote: 4-0.