Des Moines County approves bridge deck and multiple resurfacing contracts; federal funds, timing remain fluid
Summary
The Board of Supervisors approved contracts for two bridge-deck replacements and multiple resurfacing projects, with bids coming in above engineering estimates and funding split between federal-aid and farm-to-market funds. Officials warned schedules could shift if federal funding is frozen.
Get email alerts on the Roads Infrastructure topic
No spam. Unsubscribe anytime.
Des Moines County supervisors on Feb. 4 approved contracts to replace bridge decks on two structures and to resurface several county roads, accepting bids that in most cases exceeded county cost estimates.
The contracts include a bridge deck replacement package (North Gear and Danville-area bridges) with a contract amount of $2,254,835.95; a federal-aid asphalt overlay for County Highway 99 with a low bid of $4,614,489.46; a County Highway 34 resurfacing bid of roughly $2,800,000 (farm-to-market funds only); and a set of local asphalt projects (7 Ponds, Tamer Road, South Prairie Grove) with a combined low bid of $979,660.47. Supervisors voted to approve each contract during the meeting.
Why it matters: the projects will affect travel on county roads this summer and are funded through a mix of federal-aid highway dollars and local farm-to-market funds. County staff warned the board that a freeze on federal funding could pause some projects, and that residents should expect lane restrictions and periodic closures during construction.
Most important facts: county staff described the bridge work as deck replacements that preserve and reuse underlying beams, noting the work is labor intensive and came in above the county’s consultant estimate. On Highway 99 county engineers reported extensive patching—“80 or 90 patches”—ahead of a mill-and-fill overlay. The Highway 99 bid arrived with only one bidder and was about 16% over the county estimate, while other asphalt projects were 11–17% above estimates.
County staff told supervisors they had worked with the cities of Burlington and Danville to incorporate short segments of city streets into plans; the cities will reimburse the county for their portions. The board authorized the county engineer and county staff to finalize scheduling and to coordinate public notices once contractor timelines are confirmed.
On the federal funding risk, staff said that if a state or federal freeze on allocations occurs, projects that rely heavily on federal-aid funding could be paused. “If those funds were frozen, it would absolutely pause these projects,” county staff said, adding a short freeze of a few weeks would be less disruptive than a multi-month freeze.
Supervisors also discussed traffic impacts and communications: most resurfacing work will use alternating lane closures, while one short project (Tamer Road) will require a full closure; staff said they would notify directly affected residents and offer daily updates on request.
The board approved the contracts by voice votes with supervisors Shane McCampbell, Tom Broger and Jim Carrey recorded as voting yes on the motions.
Looking ahead: county staff said they will contact successful contractors to firm up schedules and will publish timing and detour information once available. Residents with immediate concerns were told to contact the county road office for project-specific updates.