Mitchell Elementary construction update: interior turnover planned May 1, exterior June 1
Summary
District staff reported construction at Mitchell Elementary is on or ahead of schedule. Interior turnover is scheduled for May 1, exterior turnover for June 1; classroom casework, finishes and specialty rooms are nearing completion.
Get email alerts on the Facility Construction topic
No spam. Unsubscribe anytime.
Tammy Carson updated the board on Mitchell Elementary on Feb. 10, saying construction is on schedule and several building elements are near completion.
Carson told the board the district expects to begin cleaning rooms on April 1, take possession of building interiors on May 1 and turn over exterior work on June 1. She described finishing work including drywall, painting, casework installation, sinks and lockers; the gymnasium painting and sound panels are mostly complete. Carson said each grade will have a distinct color scheme and described the school’s innovation pods serving adjacent classrooms.
Why it matters The timeline affects staff planning, furniture moves and the transition of students and programs to the new facility. Carson said the project is progressing quickly and invited board members to review materials and the site as finishing work is completed.
Next steps Carson said more information will be shared weekly as the project advances and asked board members to raise questions if they need specifics on rooms or schedules.