Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Transportation Infrastructure topic
No spam. Unsubscribe anytime.
Mayor, board approve roughly $1.4 million change order to finish Getwell South widening
Summary
The Southaven mayor and board approved a change order of about $1.415 million to close out the Getwell South widening project, citing unforeseen reconstruction needs on the Cherry Tree frontage and extensive undercut work.
Get email alerts on the Transportation Infrastructure topic
No spam. Unsubscribe anytime.
The Southaven mayor and Board of Aldermen voted to approve a change order for the Getwell South widening project totaling about $1.415 million, citing unanticipated reconstruction work and subsurface repairs.
The increase, presented by city staff, was described as necessary after crews discovered the Cherry Tree frontage road needed a near-complete rebuild, plus extensive undercut and additional leveling and milling to prepare final surfaces. City leaders said the combination of those items produced the bulk of the requested change order.
Why it matters: The project uses a mix of MPO (Metropolitan Planning Organization) funding and city bond proceeds. The mayor said the additional cost is a “tough blow” to capital budgets but that the city can absorb it by deferring lower-priority capital items. The mayor noted the project has consumed significant city funds since the MPO allocation was made in 2015 and urged residents to view the completed work once it reopens.
City staff said final concurrence from the Mississippi Department of Transportation (MDOT) will be required as part of the closeout process. The mayor and staff emphasized that minor final adjustments could still arise during MDOT’s final review but they do not expect further large increases.
The board approved the change order on a roll-call vote.

