Bond and construction update: Early learning academy on schedule, band room and auditorium renovations underway

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District staff told the board Feb. 3 that work on the Hedgesville Early Learning Academy, Martinsburg band-room addition and Spring Mills High press box is progressing and that Tomahawk classrooms will be ready for student move-in next week.

District construction staff provided the board an update on bond and capital projects during the Feb. 3 meeting, reporting that the Hedgesville Early Learning Academy, Martinsburg band-room addition and other projects are progressing.

Ken Tyson, the district's bond and construction presenter, said most footers at the Hedgesville Early Learning Academy have been poured, block foundations are…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans