Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Capital Projects topic

No spam. Unsubscribe anytime.

Commissioners release $276,004.47 in retainage as courthouse HVAC and related work nears completion

2219225 · February 4, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

With the courthouse and related building renovations substantially complete, commissioners approved a partial release of retainage to the contractor while holding funds for punch-list items; the work was funded with ARPA dollars.

Park County commissioners approved releasing $276,004.47 in retainage to the prime contractor for the courthouse HVAC and related building rehabilitation project as the work reaches substantial completion.

County Engineer (name provided in meeting) told commissioners the HVAC and related improvements across the courthouse addition and the Public Works building are largely finished; remaining items are mostly building-automation-system work and a few office finishes. The total contract amount reported was $7,620,629 (ARPA-funded); the amount billed to date including retainage was $7,178,177, leaving roughly $442,452 of work remaining on the contract. The retainage account held about $358,909; the contractor requested partial release of $276,004.47.

Staff said the county has received partial release waivers from subcontractors for the completed work and will advertise the statutory 44-day notice for claims as required. Commissioners approved the partial release and staff said they will return with a reconciliation change order and a final closeout that will reconcile any remaining retainage after punch-list completion.

Why it matters: the project is a major rehabilitation of facilities that had not been substantially modernized in decades. Commissioners noted the work updated HVAC, fire-code items and infrastructure and cleared up decades of wiring and other deferred maintenance.

Next steps: staff will continue to work through the punch list, finalize the 44-day advertising periods for the remaining building areas and return to the board for final closeout and release of any remaining retainage.