Parish awarded $2.6 million EDA grant for water line and Enterprise Drive widening; CSRS task order OK’d for grant administration
Summary
The parish announced an awarded $2.6 million Economic Development Administration grant to fund a 16-inch waterline and Enterprise Drive widening to support development near the hospital site; the council authorized a task order with CSRS for grant administration and staff described expected matches and timeline.
Get email alerts on the Infrastructure Grant topic
No spam. Unsubscribe anytime.
Terrebonne Parish staff told the Community Development and Planning Committee that the parish was awarded a $2.6 million Economic Development Administration (EDA) grant for a water-line installation and road-widening project designed to open development-ready land along Enterprise Drive and Westside Boulevard.
Project scope and partners: The project calls for a 16-inch water line from Enterprise Drive and Corporate Drive, turning around the identified roundabout and running along Westside Boulevard to Martin Luther King Boulevard, where the line would split. The design will create a closed loop to improve water quality and increase developable acreage in the corridor. Parish staff said the project was coordinated with the local hospital (for a proposed wellness center) and Water Works as partners; the hospital frontage portion of the line would be a partner responsibility.
Funding and match: The EDA award covers $2.6 million of a $3.2 million project. The parish noted a required 10% match (approximately $600,000 total). Staff described a potential $250,000 supplemental grant from a state economic development source that could cover the parish’s matching obligation and contribute small shares toward the hospital and Water Works costs (each estimated at about $25,000 under the verbal plan staff described).
Procurement and schedule: The committee authorized task order #7 with CSRS to perform grant-administration services for the EDA project (the CSRS task order will support grant compliance, reporting and procurement for engineering/design). Staff said they plan to procure design engineering via an RFQ and expect a construction window of roughly nine months following procurement; staff projected potential completion in late 2026 (October–November 2026) assuming design and bidding proceed on schedule.
Drainage and ancillary improvements: Councilmembers asked whether drainage and a roundabout could be included. Staff noted drainage and roundabout construction were not eligible under the awarded EDA grant but said that Terrebonne Parish’s stormwater-management design standards should improve post-development drainage. Staff also said the parish is pursuing other funding sources for drainage or roundabout work.
Why it matters: The work would extend water infrastructure and roadway improvements to enable larger developable parcels in a corridor identified by staff and project partners — potentially supporting hospital and other employment-generating projects that meet EDA job-creation criteria.
Direct quote (transcript): "This would tie it all together, have a complete closed loop so we get better water quality because it's a... loop system. It opens up that entire corridor for development," (Mister Pulaski, engineering staff).
Next steps: The committee voted to authorize the CSRS task order and proceed with engineering procurement; staff will seek supplemental matching grants and advance design work toward a bid package and construction timeline.
Limitations: Staff presented a verbal plan for supplemental state funding and anticipated partner contributions; the transcript records the parish’s expectation but not executed match agreements or signed engineering contracts.