Architects present two‑summer plan, $5 million media‑center component for Grayslake CCSD 46 facilities work
Summary
Wold Architects updated the Grayslake CCSD 46 board on schematic design and a phased construction timetable that would split abatement and heavier construction over summer 2026 and summer 2027; the district plans roughly $5 million for media‑center improvements within an $11 million bond sale.
Wold Architects on Wednesday told the Grayslake Community Consolidated School District 46 Board of Education that the district’s media‑center redesigns are moving from schematic design into design development and that construction will be phased across two summers to accommodate asbestos abatement and budget constraints.
The update came during the board’s Jan. 29 meeting at Frederick School. “We’ve wrapped up our core planning group process, which is really the schematic design effort, and we’re moving into what’s called design development,” said Matt, a Wold Architects representative, describing the next steps that will gather user‑group and principal input.
The architects said the district intends to complete detailed drawings and user‑group reviews in spring and to issue construction bids in October with a hoped‑for construction award at the November board meeting. The design team recommended splitting the work so that asbestos abatement at three…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat