Mayor Mathis outlines recovery progress; sheriff warns jail overcrowding and transport costs strain resources
Summary
Mayor Mathis reported relief distributions, state/federal coordination and a major bridge replacement covered by state aid; the sheriff reported severe jail overcrowding and transport burdens that could worsen if the county’s backup facility is closed.
Get email alerts on the Disaster Recovery topic
No spam. Unsubscribe anytime.
Mayor Mathis updated the Cocke County Board of Commissioners on recovery efforts, federal-state coordination and funding for infrastructure repairs, while the county sheriff described mounting operational strain in the jail system.
Mathis said the county, the city of Newport and a local partnership have distributed more than $800,000 in direct relief to residents and businesses — roughly 73 homeowners and 29 businesses — with additional funds and property-tax payments to follow. He said the county has arranged FEMA, Army Corps and contractor teams to collect debris, assess hazards along private roads and seek FEMA exemptions for debris removal where homeowners lack responsibility under current guidelines.
Mathis said a fully destroyed county bridge (Mall Creek Bridge) that had been estimated to cost roughly $7.8 million to replace will be repaired with state and federal assistance and that the county will not bear local tax costs for that bridge. He said proposed state-level legislative adjustments could reduce the county’s share of recovery costs on some projects from about 12.5% to roughly 5%, creating substantial fiscal relief.
The sheriff addressed the commission about the jail’s post-flood condition. He said the county’s 52-bed workhouse has been housing as many as 98 inmates, that the county is transporting inmates to other counties (sometimes long distances) and that plumbing and fire-safety issues at backup facilities create a potential for a forced closure by the state fire marshal. The sheriff said transporting inmates five to seven times per day results in increased costs for overtime, fuel and vehicles and warned that if the backup facility is ordered closed on inspection, the county will need immediate transfer arrangements with partnering counties.
Commissioners asked for updates on the number of displaced residents, FEMA registrations and direct housing placements. Mathis said FEMA’s regional estimates showed roughly 50 people living without shelter across the whole affected region but that county records showed no confirmed reports of people sleeping in tents in Cocke County; he said direct housing applications and temporary housing approvals were ongoing and provided staffing and direct-housing counts from the FEMA regional reports.
Commissioners thanked volunteers and local organizations for relief work and stressed the need for coordinated work to avoid duplicative efforts. The board directed staff to continue coordinating with FEMA, Army Corps and the state and to report back on jail inspection status and inmate-transport costs.