Page County awards $135,172 j64 guardrail contract; adopts digital-signing resolution
Summary
The Page County Board of Supervisors voted to award a j64 guardrail contract to Dave Gripp Construction for $135,172 and approved Resolution 10, 2025 to delegate digital signing authority for DOT contracts; engineering staff also updated the board on bridge work and baseline road surveys tied to the Shenandoah Hills wind project.
Get email alerts on the Roads Contracts topic
No spam. Unsubscribe anytime.
The Page County Board of Supervisors voted to award a j64 guardrail contract to Dave Gripp Construction for $135,172 and approved Resolution 10, 2025 delegating digital signing authority for the contract, commissioners said at their meeting.
The actions matter because the guardrail work addresses a county road safety project and the resolution clears a technical hurdle for the Iowa Department of Transportation’s paperless contracting process, allowing county officials to sign DOT-required documents electronically.
JD King, Page County Engineering, told the board crews are continuing weather-dependent operations, focusing on potholes, watch boards around intersections and bridge approaches. “The Shenandoah Hills wind project has all roads designated,” King said. “We have a video survey of that as a baseline.” King described the survey as nearly complete and said the county will likely run another iteration before wind-project work begins to document pre-construction conditions.
King also updated the board on a bridge project north of Essex, reporting crews poured concrete in the north abutment and were scheduled to place concrete in the south pier cap the following day; work on the north pier was proceeding through shale down to hard rock.
On the j64 guardrail project, King said the county received three bids ranging from roughly $135,000 to $172,000. The low bid, $135,172, came from Dave Gripp Construction of Williamsburg, Iowa. A motion to award the contract to Dave Gripp Construction was made and seconded; the board voted unanimously to approve the award.
The board then approved Resolution 10, 2025, which delegates digital signing authority for the contract to comply with DOT’s paperless procedures. County officials described the resolution as routine and said a copy had been provided to the county auditor.
The board also heard routine equipment and maintenance updates from King, including service work on a sheriff’s pickup and landfill machine and shoulder-rock hauling to a stockpile on M-48.
Board members did not request further delay on the contract award or the resolution and moved to the next agenda items after approval.