ODOT-led Sunbury Parkway Phase A to go out to bid; city outlines clearing and funding timeline
Summary
City Administrator Jake Hennessy told council Jan. 29 that ODOT expects to open bids for Sunbury Parkway phase A in June with construction to begin within 90 days of award; phases B and C are being designed and may use local TIF and developer funding, while phase D funding remains uncertain.
City Administrator Jake Hennessy updated council on Jan. 29 about planning and near-term steps for Sunbury Parkway, saying the Ohio Department of Transportation expects to advertise and open bids for Phase A in June with contract award soon after and dirt-moving within roughly 90 days of award.
Hennessy said the public can expect preliminary clearing and utility work near the Way Station area before large-scale…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat