GO Bond update: Fire station, East Mesa complex and housing projects progress; some schedule delays
Summary
City staff reported construction progress on Fire Station No. 9 (10% complete), delays and upcoming work at the East Mesa Public Rec complex, park improvements pending an IBWC lease, and status updates on affordable housing projects financed or supported by 2022 GO bonds.
Las Cruces — City public-works and housing staff on Jan. 27 gave a quarterly update on projects funded or continued with the 2022 general-obligation (GO) bond, reporting construction starts, partial completions and scheduling changes.
David Sedillo, public works director, said contractor White Sands Construction began work on Fire Station No. 9 on Oct. 28 and the project is “currently at 10% completion,” with earthwork, sewer rough-ins and electrical rough-ins finished and foundation rebar work upcoming. Sedillo said the estimated completion date for the station is February 2026.
On park improvements, Sedillo said a contract for El Yunque and Telbrook park improvements (packet labels vary) was awarded to Manson Construction for approximately…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat