Commissioners approve two T-SPLOST dirt-road paving design contracts totaling about $1.4 million

2157625 · January 28, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved not-to-exceed design contracts with Kimley-Horn ($554,900) for Batch 1 and American Engineers ($860,544) for Batch 2 of FY25 dirt-road paving projects, both funded by T-SPLOST. Commissioners discussed aggressive schedules, large right-of-way needs and additional task orders for final design.

Brad Deal, county engineer, told the board he organized FY25 dirt-road paving into two batches to speed delivery and improve efficiency and asked commissioners to approve design task orders for both batches funded by T-SPLOST.

"We were gonna consult out the right of way as well because I think we're looking at somewhere around 200 property owners on this batch of roads," Deal said, describing Batch 1 and the compressed schedule. He said Batch 1 includes Floyd Clark Road, Deer Run Court/Lane and Prather Road (about 0.8 mile) and Grimshaw Road/Lane; the Kimley-Horn contract covers preliminary design tasks in a not-to-exceed amount of $554,900, with additional task orders expected for final design after right-of-way resolution.

For Batch 2, which covers another cluster of roughly seven roads including RL Lee Road, JR Parker Road, Schumann Road and a Lakeside-Estates grouping, staff recommended American Engineers Inc. in a not-to-exceed amount of $860,544. Deal said firms were selected through a qualifications-based process, that proposals included technical approaches and staffing commitments, and that right-of-way acquisition will be consulted out because of the large number of property owners.

County Manager (interim) and CFO told commissioners that available T-SPLOST funds could cover the contracts and that unused funds from earlier, slower projects allowed a more aggressive schedule this year. Commissioners praised the approach as a way to accelerate delivery of roads that previously took years to advance.

The board voted to approve both contracts; motions passed on unanimous voice votes.