Finance committee approves trail extension, golf‑course pond repairs and asset‑management software; FY24 audit to be presented Feb. 10
Summary
On Jan. 27 the committee approved three construction and procurement contracts — a Tierra Contenta trail extension, repair of irrigation ponds at Marty Sanchez Golf Course, and a five‑year asset‑management software purchase — and staff announced the FY24 audit presentation dates.
Get email alerts on the Committee Approvals Jan27 topic
No spam. Unsubscribe anytime.
The City of Santa Fe Finance Committee on Jan. 27 approved three procurement contracts on the consent agenda and heard that the city’s FY24 audit has been released and will be presented at the committee’s Feb. 10 meeting and to the governing body on Feb. 12.
Votes at a glance
• Tierra Contenta Trail Extension Phase A (Agenda item G): Contract awarded to GM Emulsion LLC for construction of the Tierra Contenta Trail Extension Phase A in the amount of $1,111,917 (excluding New Mexico gross receipts tax), 22‑year term noted in the agenda. Staff said the project is a 10‑foot‑wide concrete trail totaling 2,006 linear feet (about 0.38 mile). Estimated construction time is six to nine months, subject to weather and federal/state preconstruction scheduling; warranty for capital projects is one year. Because the project is federally funded it must follow Buy America/Build America requirements, which staff said can add to material costs.
• Marty Sanchez Golf Course and Municipal Recreation Sports Complex pond repairs (Agenda item L): Contract awarded to Mountain West Golfscapes Inc. to repair irrigation supply and ornamental ponds for compliance with a corrective action plan in the amount of $2,213,247.69 (excluding NMGRT) for a three‑year term. Staff said the installed pond liner material will be a 60‑mil fabric with a manufacturer defect guarantee of five years and an average life expectancy of 20–25 years; the largest ponds serve irrigation for the golf course and adjacent sports fields.
• Asset management software and implementation services (Agenda item shown as Virtosoft/OpenGov): Contract awarded for asset‑management software and implementation not to exceed $1,913,591.72 including NMGRT for a five‑year term. Staff said the city conducted a formal evaluation process including scripted vendor demonstrations and reference checks; the selected vendor (identified in the evaluation as OpenGov) provided satisfactory references from other municipal users and staff included operational units in the selection to increase adoption success.
Each contract passed on roll call votes. Recorded affirmative votes on these items included Councilors Cassatt, Lindell, Faulkner, Lee Garcia and Chair Romero Wirth.
Staff announced that the city’s FY24 audit was released and will be presented by Carr, Riggs & Ingram (as stated) at the Feb. 10 Finance Committee meeting and to the governing body on Feb. 12; the audit report is posted on the State Auditor’s and the city’s websites.