At its Jan. 27 business meeting the Racine Unified School District Board approved a package of financial and construction measures, accepted monitoring reports with one dissenting vote, and handled routine consent business.
Get email alerts on the Board Actions topic
No spam. Unsubscribe anytime.
The Racine Unified School District Board of Education took multiple formal actions Monday, approving financing steps, construction early‑bid packages, a guaranteed maximum price for a school project, a construction‑management software renewal and routine consent items. The board also accepted monitoring reports for math and science; one board member recorded a no vote on that acceptance.
Key outcomes:
- Agenda amendment: The board amended the meeting agenda to move the Red Apple facility item earlier; the procedural motion passed unanimously (7 yes, 0 no).
- Red Apple naming: The board accepted the facility renaming committee recommendation to retain the name Red Apple for the school relocating to Center Street (6 yes, 1 no).
- Open enrollment seats: The board approved the open enrollment space designation for the 2025–26 school year as presented (7 yes, 0 no).
- Financing resolution: The board approved a resolution authorizing issuance of not‑to‑exceed $22,000,000 promissory notes and establishing parameters for sale of not‑to‑exceed $135,000,000 general obligation promissory notes (7 yes, 0 no).
- Defeasance/transfer of funds: The board approved a resolution establishing an escrow account and defeasing certain general obligation refunding bonds dated April 5, 2023. Administration said $16,600,000 of future bond payments were defeased, producing estimated bond interest savings of about $10,000,000 (7 yes, 0 no).
- Early bid packages: The board approved early bid packages for Gifford K–8 ($1,292,132) and Wadewitz Elementary ($1,196,977) (each motion passed 7–0).
- Gilbane Guaranteed Maximum Price (Fred Elementary): The board approved Gilbane Inc.'s Guaranteed Maximum Price for construction at Fred Elementary of $10,843,484 and a total project budget of $13,941,501 (7 yes, 0 no).
- Procore renewal: The board approved a Procore construction‑management software renewal for $205,687.47 (7 yes, 0 no).
- Superintendent and board consent agendas: Both consent agendas passed in whole; a single superintendent item (8f) was separated for discussion and then the remainder passed (consent motions passed 7–0).
- Monitoring reports (math and science): The board accepted the monitoring reports as "making reasonable progress" with exceptions noted; Board Member Coe recorded the lone no vote on that item (6 yes, 1 no).