Phase 1 of auditorium refresh complete; phases 2 and 3 to be presented to board
Summary
District staff said Phase 1 work on two auditorium projects is nearly finished and that phases 2 and 3, estimated at about $460,000 and $250,000 respectively, will be brought to the board for approval once vendor proposals are finalized.
Get email alerts on the Facility Renovation Auditorium topic
No spam. Unsubscribe anytime.
Perkiomen Valley School District staff told the Safety and Operations Committee that phase 1 of auditorium work is nearing completion and that the district will seek board approval in February to move forward with phases 2 and 3, pending final vendor proposals.
A staff member said the vendor will finish phase 1 items and that a rigging inspection is expected by the end of the month. Phase 1 is "at or a little under budget and is completed on time," the presenter said. The staff estimate for phase 2 is about $460,000 with a two- to three-month installation window; phase 3 is estimated at roughly $250,000 with about two months of installation time.
"The phase 1 is nearing its completion...the rigging inspection, which we anticipate to be completed by end of this month," a staff member said. "We anticipate based on the previous estimates...phase 2 to cost around $460,000, with a timeline of 2 to 3 months for that installation. And the phase 3 is around $250,000 with a timeline of about 2 months for the implementation."
Staff said they will present updated proposals to the committee and, if the committee concurs, both phases will be bundled for full board approval in February. The presenter noted some line items are needs and others are wants; the final vendor proposals will determine which tasks proceed in the requested timeline.
Ending: Committee members agreed to place phases 2 and 3 on the February board agenda once updated vendor proposals are received and the committee signs off on scope and budget details.