Consultants unveil high-level vision and eight-month schedule for Carson Civic Center redevelopment plan
Summary
Z & K Consultants and team presented a conceptual master plan and specific-plan process for a proposed Civic Center redevelopment. The presentation outlined alternatives, a preferred high-level vision (city hall, performing arts center, hotel, housing), and an eight-month timeline to produce a specific plan and environmental and entitlement-ready
Get email alerts on the Land Use topic
No spam. Unsubscribe anytime.
Consultants working for the City of Carson presented an overview of the proposed Civic Center redevelopment specific plan and master plan process at the Jan. 21 council meeting.
Z & K Consultants introduced the project team and described the work program: prepare a civic center specific plan to streamline entitlements, program municipal facilities (city hall, community and performing arts uses), develop high-level concept designs, produce cost estimates and prepare environmental documentation to support redevelopment. Larry Schlosberg of Gruen Associates and project manager Britney Dune presented vision imagery and a preferred concept.
Why it matters: the Civic Center site is an 11-acre property now dominated by surface parking, the existing city hall and event center. The consultant team showed a high-level concept that includes a new City Hall, a performing arts center, housing, and a high-rise hotel among alternatives. The specific plan is intended to set planning, zoning and urban design rules that would streamline future development and provide cost and program certainty for major civic investment.
Schedule and next steps: the consultants outlined an approximately eight-month schedule to produce the specific plan, programming, concept designs and preliminary cost estimates, with public engagement milestones. The project team said the work will include economics, traffic, environmental analysis, infrastructure and cost estimating as well as a performing arts programming component. The item was informational; the consultants said they would return with more detailed drafts and additional council briefings.
Council comments: no substantive policy change or vote was requested; council members thanked the team and indicated they expected ongoing briefings and public outreach.