Sewer separation bid at $2.4M, Broadhead sewer and other infrastructure projects move forward
Summary
Engineer reported the C-20 sewer separation low bid at $2.4 million and said Gateway will discuss bids before an award. Broadhead sewer project remains contingent on EPA environmental review. Borough also reported completed public-stairs work, planned storm-retention inspections, and a public-works building sewer-lateral project.
Crafton Borough Engineer Mike Keenan updated council on multiple infrastructure projects at the Jan. 23 meeting, including a low bid for the C-20 sewer separation project, the Broadhead sewer project, storm-sewer retention work at Craft Elementary and the public-works building sewer lateral.
Keenan said bids for the C-20 sewer separation project were opened Jan. 14; three bids were received and the lowest was $2,400,000. Gateway — the borough's engineering partner — asked to meet with borough staff…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat