San Luis council approves nearly $3 million membrane purchase for West Wastewater Plant expansion

2146658 · January 23, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council approved awarding the membrane bioreactor equipment purchase for the West Wastewater Treatment Plant Expansion to Kubota Membrane USA in a bid of $2,998,000 and authorized staff to finalize contract terms to be spent over the next fiscal year.

The San Luis City Council approved the procurement of the main membrane bioreactor (MBR) process equipment for the West Wastewater Treatment Plant Expansion on Jan. 22, accepting a recommendation from the city's engineering consultant and authorizing staff to finalize contract terms.

Jorge Perez, Assistant Director of Public Works, told the council the project is at roughly 30% design and that the city solicited proposals for three major pieces of equipment for the expansion. He said the consultant evaluation ranked Kubota Membrane USA highest; the recommendation memorandum cited a proposed price of $2,998,000 for the membrane system.

Perez said staff is seeking approval now because equipment delivery can take an extended period. He told the council the manufacturer’s delivery lead time would take “between 38–50 weeks.” The council approved a motion authorizing the purchase “in an amount not to exceed $2,998,000” and directed staff to finalize contract terms; the approval is structured to allow the expense to be spent over the next fiscal year.

Why it matters: The MBR system is a core treatment technology for the plant expansion and is the first of three major procurements. Securing long-lead equipment early aims to keep the expansion schedule on track.

Next steps: Staff will finalize contract language and coordinate delivery timing with the consultant and contractor as the project progresses through design and construction planning.