Macedonia to bid 2025 sidewalk program; 390 property owners to get notices, city offering interest-free installments

2146372 · January 23, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City council approved a resolution to advertise bids for a citywide 2025 sidewalk repair program. About 390 property owners will receive letters; homeowners may repair privately by June 1 or have the city contract repairs and be billed via a three-year, interest-free assessment plan.

Macedonia City Council on Jan. 23 approved a resolution authorizing the city engineer to prepare plans, specifications and to advertise for bids for the 2025 sidewalk program.

Council members and staff said the program expands last year’s work beyond the Crow area to cover the rest of the city and follows inspections that identified roughly 390 properties with defective sidewalk slabs.

Commissioner Monaco, who presented the item, said homeowners will receive letters identifying specific slabs that need repair and will have two options: obtain a free permit and hire their own contractor by June 1, or let the city hire a contractor and have the work added to their property tax assessment. “The deadline is June 1st to, to apply for a permit, which are gonna be free,” Monaco said.

Monaco and other council members emphasized that the city’s program is intended as a safety measure and to avoid private lawsuits arising from trip-and-fall injuries. Monaco noted the city’s code places maintenance responsibility on property owners and that the city’s process follows sealed competitive bidding.

On payment, council said the city will allow three interest-free installments so property owners can spread costs. A council member said, “The city is generous enough to allow 3 years for payment. 3 installment. The first 1 will not be due until either June or July 2027,” with subsequent payments due in 2028 and 2029. The city will provide a revised, detailed cost to each homeowner after bids are opened.

Council members also said the city will post bid openings publicly and encouraged residents to contact the billing department with questions.

The resolution passed on a voice vote. The item returns to council after bids are received and staff prepares final costs and assessments.