Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Capital Projects Wickline topic

No spam. Unsubscribe anytime.

Commission approves Wickline Improvements change orders but removes proposed aluminum rail change

2146370 · January 22, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The commission approved change orders 1–8 for the Wickline Improvements Project but directed removal of proposed change order 9 (aluminum rail) so the project retains the original stainless-steel railing specification.

The Flagler Beach City Commission voted Jan. 23 to approve change orders 1 through 8 for the Wickline Improvements Project (Project 539) and to remove proposed change order 9 from the resolution after discussion about material specification.

Why this matters: the Wickline Center has a history of project scope and budget issues for past improvement efforts; commissioners emphasized stricter oversight and adherence to “not to exceed” amounts to prevent unapproved scope creep.

What the commission approved

- The resolution presented included change orders 1–9 totaling $20,866.80 in the agenda text, but a commissioner asked to delete section 2 of the resolution to remove change order 9. Staff confirmed the original contract called for stainless steel railing, not aluminum, and the commission agreed to strike Section 2 (the proposed change order 9) and approve only change orders 1–8.

- City staff explained the change orders arose after the original purchase order had been posted at the full $110,000 line item for the project rather than the approved contract amount (about $65,000). The city manager told the commission staff will tighten internal controls so future not-to-exceed amounts are not exceeded without explicit commission approval.

Commission concern and context

Commissioners criticized prior spending and described the building’s improvement history as problematic. The city manager acknowledged the error in the posted purchase order and said staff will ensure future change orders come to the commission when required by the original not-to-exceed amount.

Voting

The motion to approve Resolution 2025-07 with section 2 removed passed unanimously. Staff will proceed to implement change orders 1–8 and will not approve the aluminum railing change order without a future commission action.

Ending

The commission’s action approves the documented work already completed under change orders 1–8 and instructs staff to maintain tighter fiscal controls and clearer change-order reporting in future projects.