Splash pad piping and concrete work complete; testing scheduled, liquidated damages accruing

2143569 · January 23, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public Works reported that piping and concrete work for the city splash pad are complete, testing and balancing is planned by the end of February, and the facility could be functional by April 1; liquidated damages of about $14,900 have accrued to date because of construction delays.

Project Engineer Patrick Fry told the Parks and Public Works Committee on Jan. 7 that piping and most underground work for the city’s new splash pad are complete, the concrete has been poured and staff plan to begin testing and balancing by the end of February.

"We're just letting the concrete cure, and then we're gonna be putting the features up," Patrick Fry said. The feature set includes about 48 water-play elements; once concrete curing and feature installation are…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans