Council ratifies $247,000 change order for Adams Gas Main extension; staff cites missed bid quantity

2141506 · January 22, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved Change Order No. 2 to the Moss Welding contract for the Adams Gas Main Extension Projects, a $247,000 adjustment that staff said included $193,000 attributable to a missed quantity in the original bid package; the board recorded the vote in the transcript as 7 to 6.

The Board of Mayor and Aldermen on Jan. 21 ratified Change Order No. 2 to the Moss Welding contract for the Adams Gas Main Extension Projects, recording the vote in the transcript as "Motion passes 7 to 6."

Ryan, a city staff member, told the board the project had been completed and the change order consists largely of field changes encountered on site and a quantity that was not included properly in the bid package. "A large item was due to a, an item not being included and accounted for properly in the bid package," Ryan said, and he added that the $193,000 portion of the $247,000 change order is tied to that missed quantity.

Ryan said the project overall came in under budget originally and that funds are available to cover the change order. He said the staff is working with the engineering firm that prepared the bid package to determine how the omission occurred, noting some of the employees who prepared the bid are no longer with the firm.

Alderman Bradley moved to approve the change order and Alderman Hubbard seconded. The transcript records the motion as passing 7 to 6. The board directed staff to process the change order payment and to continue discussions with the engineering firm to determine responsibility for the missed quantity.