Deltona staff outline plan to plug artesian ‘boil,’ restore Lakeshore 4B intake and boat ramp

2141025 · January 22, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

At a Deltona City Commission meeting, utility staff updated commissioners on the Lakeshore 4B aquifer storage and recovery project and an artesian "boil" that forced the nearby boat ramp to close and stalled the project.

At a Deltona City Commission meeting, utility staff updated commissioners on the Lakeshore 4B (Lakeshore Strahl) aquifer storage and recovery (ASR) project and the artesian "boil" that forced closure of the nearby boat ramp and delayed the project.

The presentation outlined the project’s phases, explained St. Johns River Water Management District’s direction that the boil be plugged, and described immediate steps staff will seek: dewatering the intake area, hiring geotechnical contractors to locate and grout the artesian flow, dredging the ramp approach and removing sheet piling, and pursuing grants and intergovernmental partners to offset costs.

The city’s Deputy Utility Director, Jim Parrish, described the project as a multi‑phase effort that began with a rapid infiltration basin and an Alexander Avenue treatment site (the 4A work) and continued to the 4B intake structure. Parrish said the city has “spent approximately $5,000,000 on this project to date,” and that site restoration alone is estimated at about $300,000. He told commissioners the latest preliminary estimate to finish the 4B work is roughly $4 million to $5 million, and that the district has grant programs that could cover the grouting portion; Parrish said the geotechnical investigation would be a city expense.

Why it matters: the project was intended to pull nutrient‑rich water from Lake Monroe, treat it, and recharge the aquifer to secure credits in Deltona’s consumptive‑use permit. Parrish said that without the ASR capacity the city risks stricter limits on groundwater withdrawals because the district counts artesian losses against a jurisdiction’s consumptive‑use allocation.

Details of the problem and proposed work: while building the intake/wet well at Lakeshore, contractors encountered flowing artesian water on the lakeside that could not be plugged by temporary measures. St. Johns Water Management District has directed the city to remove water from the work area so the district can measure flow rates and accept a technical plugging plan. Parrish said the district “wants us to dewater the site” so engineers can determine whether the flow is tens of gallons a minute or hundreds, and then recommend grout placements to seal voids feeding the boil.

Parrish said the technical plug is done by grouting voids identified by geotechnical engineers, and that while the district’s grant money can cover the grouting material and work in some cases, the geotechnical investigation and contractor mobilization are generally not covered and would be a city cost. He listed other agencies that must be consulted on restoration plans, including the Florida Department of Environmental Protection and the U.S. Army Corps of Engineers.

Costs, benefits and timeline: staff described three types of costs: (1) money already spent (Parrish said about $5 million), (2) site restoration (sheet pile removal, dredging) estimated at about $300,000, and (3) the remaining work to complete the ASR project, preliminarily estimated at $4–5 million. Parrish said staff is exploring partnerships with Volusia County and neighboring cities and pursuing additional grants. On timeframe, staff suggested a planning, contracting and construction window of months rather than weeks; commissioners and staff discussed a ballpark completion under a year if contracts proceed promptly.

Commission response and direction: commissioners repeatedly pressed staff on alternatives (moving intake, floating ramp), on whether prior geotechnical work was done and why veins were missed, and on community impact. Commissioner Halligan asked why the city would pull lake water rather than use closed‑basin sources; staff cited distance and pipe‑costs as constraints and noted the regional consumptive‑use requirements. Commissioner Villalvaasquez emphasized that Deltona participated as part of a West Volusia consortium and said the project responds to St. Johns’ requirement for alternative water projects.

Public comment: neighbors asked for faster cleanup and restoration of the park and boat ramp. Resident Rachel Amoroso, who said she manages a nearby condominium association, urged the city to remove signage promising earlier reopening and to restore trees and viewing areas. Resident Jim Pesha urged the city to consider demand‑side options such as landscaping regulations to reduce irrigation demand; he asked, “Did you know that 50% of our potable water that we create is used for irrigation?” and suggested native landscaping as an alternative to reducing nutrient runoff.

Next steps: staff asked the commission for consensus to begin consultant procurement and limited bid steps (not to encumber budgeted funds immediately), to obtain firm cost proposals for dewatering, geotechnical investigation, grouting and dredging, to pursue matching grant funding, and to return contracts to the commission for formal approval. Commissioners verbally agreed; staff will bring task authorizations and contract approvals back to the commission before work begins.

The city also said Applied Aquatics will begin manual removal of overgrowth at the site so the area is not an eyesore while the technical work proceeds.

Ending: staff emphasized that St. Johns River Water Management District’s requirement to plug the boil is a gating constraint: the district’s acceptance of the plugging method and measured flow rates will shape the final engineering plan. Staff promised to return with consultant task authorizations, firm cost estimates and a recommended schedule for dredging and ramp restoration.